N191-027
|
TITLE:
Conductivity, Temperature, Depth (CTD) Sensor for Ohio Class Ballistic
Missile (SSBN), Ohio Class Guided Missile (SSGN), and Columbia Class Submarines
|
TECHNOLOGY
AREA(S): Battlespace, Electronics, Sensors
ACQUISITION
PROGRAM: PMS 401, Submarine Acoustic Systems Program Office
OBJECTIVE:
Develop an effective Conductivity, Temperature, Depth (CTD) sensor for the Ohio
Class SSBN, Ohio Class SSGN, and Columbia-class submarines.
DESCRIPTION:
The Navy has a need to improve the capabilities of its current CTD sensors to
acquire environmental data aboard its deployed submarines. These sensors
measure conductivity, temperature and pressure to estimate the speed of sound
and seawater salinity and density. It is imperative that the data accurately
represent ambient conductivity, temperature, and depth conditions with no
latency and with high degree of accuracy. The Navy�s CTD was a form factor
replacement for the legacy sound speed sensor and designed to be installed into
the sensor chamber on 688(i)-class submarines. This is not an optimal CTD
system configuration for SSGN/SSBN, as it causes inadequate flow to be directed
at the CTD sensor resulting in an erroneous measurement of sound speed
profiles. A CTD specifically designed for use in SSN sea chests is hampering
the ability of SSBN/SSGN and eventually Columbia-class submarines to accurately
estimate local sound speed and water density. A sensor designed specifically
for the Ohio SSBN/SSGN and Columbia submarine classes is required and will
allow for the acquisition of more accurate data. As such, while CTD sensors are
commercially available for purchase, they are not specifically designed for the
mounting arrangement and unique flow requirement of the
SSBN/SSGN/Columbia-class submarines as detailed in platform-specific plans.
The new sensor will fit a maximum envelope form factor of an 18-inch by 18-inch
by 18-inch cube to minimize the need to modify the current sensor�s sea chest,
and will also be designed to ensure adequate flow to the CTD sensing elements.
The design of a sensor that is optimized for the SSBN/SSGN/Columbia class sail
CTD intake vents is necessary to enable accurate sensing of these important
parameters. This will enable an accurate sound velocity profile to be used in
sonar tactical aids. It will enable better weapon presets and better ballast
control for both manual and automatic ship handling during assents to periscope
depth and hovering operations. This both enhances mission performance and helps
to reduce broaching and associated vulnerabilities.
Specific requirements include the following:
1) The conductivity sensor must achieve an accuracy after stabilization of less
than 28 �S/cm (micro-Siemans/centimeter) RMS error (threshold) or 14 �S/cm
(goal).
2) The temperature sensor must achieve an accuracy after stabilization of less
than 0.28�C root mean square (RMS) error (threshold) or 0.14�C (goal).
3) The pressure sensor (supporting depth determination) must achieve an
accuracy after stabilization of less than 0.3 decibars (i.e., 50 kPa) RMS error
(threshold) or 0.2 decibars (i.e., 20 kPa) (goal).
4) All sensors (temperature, conductivity, and pressure) must achieve a
stabilized state after any change in ambient conditions in less than 12 seconds
(threshold) and 6 seconds (goal). A stabilized state is equivalent to 95% of
the steady state level approached with unlimited wait time.
5) The maximum delay in passing sample water from the free stream outside of
the hull boundary through a duct (limit IAW ship drawings, 18-inches)onto any
sensor head must be 3 seconds (threshold) or 1.5 seconds (goal) when the boat
speed through the water is 5 knots or greater.
6) The CTD system must meet Military Standard (MILSTD) 461 electromagnetic
noise requirements for conducted and/or radiated emissions.
7) The CTD system must meet MILSTD 901D requirements for shock qualification
standards and MIL-STD-810 Environmental Engineering Considerations and
Laboratory Tests.
The Phase II effort will likely require secure access, and NAVSEA will process
the DD254 to support the contractor for personnel and facility certification
for secure access. The Phase I effort will not require access to classified
information. If need be, data of the same level of complexity as secured data
will be provided to support Phase I work.
Work produced in Phase II may become classified. Note: The prospective
contractor(s) must be U.S. Owned and Operated with no Foreign Influence as
defined by DoD 5220.22-M, National Industrial Security Program Operating
Manual, unless acceptable mitigating procedures can and have been be
implemented and approved by the Defense Security Service (DSS). The selected
contractor and/or subcontractor must be able to acquire and maintain a secret
level facility and Personnel Security Clearances, in order to perform on
advanced phases of this contract as set forth by DSS and NAVSEA in order to
gain access to classified information pertaining to the national defense of the
United States and its allies; this will be an inherent requirement. The
selected company will be required to safeguard classified material IAW DoD
5220.22-M during the advance phases of this contract.
PHASE
I: Develop a conceptual design of a CTD optimized for installation in a
SSBN/SSGN sea chest. Demonstrate feasibility of the design through testing,
modeling, and/or simulation. Show feasibility of deployment on a submarine
through demonstration of fit to the form factor as well as demonstration of
transmission through cable length that would be required on a submarine in the
required timeframe. Develop a Phase II plan. The Phase I Option, if exercised,
will include drawings, schematics, and financial plan to build the prototype in
Phase II for the proposed system.
PHASE
II: Develop and deliver a prototype CTD sensor. Demonstrate that the system
will fit into the existing sea chest. Prepare a Phase III development plan to
transition the technology to Navy use. Once a prototype is produced, or if a
detailed model is produced, complete testing to verify performance criteria has
been met.
It is probable that the work under this effort will be classified under Phase
II (see Description section for details).
PHASE
III DUAL USE APPLICATIONS: Support the Navy in transitioning the CTD sensor to
Navy use. Deliver the sensor to Naval Undersea Warfare Center Division Newport
(NUWCDIVNPT) for final inspection. Send a representative to accompany
NUWCDIVNPT personnel for installation onto a SSBN, SSGN, or Columbia-class
submarine. Perform further receipt-testing of the installed sensor to verify
the performance requirements were met.
REFERENCES:
1.
"Conductivity, Temperature, Depth (CTD) Sensors.� Ocean Instruments, Woods
Hole Oceanographic Institution, Woods Holes, MA, 26 January 2018,� http://www.whoi.edu/instruments/viewInstrument.do?id=1003
2.
Urich, Robert J. �Principles of Underwater Sound.� Peninsula Publishing,
Westport, CT, 1992, https://www.amazon.com/Principles-Underwater-Sound-Robert-Urick/dp/0932146627
KEYWORDS:
Conductivity, Temperature, and Depth (CTD); SSBN and SSGN Sensors; Columbia
Class Submarine; Speed of Sound; Underwater Acoustics; 688(i)-class Submarines
** TOPIC NOTICE **
These Navy Topics are part of the overall DoD 2019.1 SBIR BAA. The DoD issued its 2019.1 BAA SBIR pre-release on November 28, 2018, which opens to receive proposals on January 8, 2019, and closes February 6, 2019 at 8:00 PM ET.
Between November 28, 2018 and January 7, 2019 you may communicate directly with the Topic Authors (TPOC) to ask technical questions about the topics. During these dates, their contact information is listed above. For reasons of competitive fairness, direct communication between proposers and topic authors is not allowed starting January 8, 2019 when DoD begins accepting proposals for this BAA.
However, until January 23, 2019, proposers may still submit written questions about solicitation topics through the DoD's SBIR/STTR Interactive Topic Information System (SITIS), in which the questioner and respondent remain anonymous and all questions and answers are posted electronically for general viewing until the solicitation closes. All proposers are advised to monitor SITIS during the Open BAA period for questions and answers and other significant information relevant to their SBIR/STTR topics of interest.
Topics Search Engine: Visit the DoD Topic Search Tool at www.defensesbirsttr.mil/topics/ to find topics by keyword across all DoD Components participating in this BAA.
Proposal Submission: All SBIR/STTR Proposals must be submitted electronically through the DoD SBIR/STTR Electronic Submission Website, as described in the Proposal Preparation and Submission of Proposal sections of the program Announcement.
Help: If you have general questions about DoD SBIR program, please contact the DoD SBIR Help Desk at 800-348-0787 or via email at [email protected]
|